News Update (01-12-2013) Update Berita (01-12-2013)
Training & Factory Acceptance Test in China, November 2013

Staff training and factory acceptance test in China in November 2013

Pelatihan staf dan uji penerimaan pabrik di RRC bulan November 2013.

Boiler about to be unloadedBoiler is in place

Left: the boiler about to be unloaded.
Right: the boiler already set in place.

The boiler which plays an important role in sterilization, is the heart of a factory that manufactures IV solutions.

Kiri: Boiler akan diturunkan dari transport.
Kanan: Boiler telah terpasang di tempatnya.

Boiler, yang memegang peranan penting dalam proses sterilisasi, adalah jantung operasional pabrik cairan infus.

Plate about to be installedPlates which are already installed

Left: a plate about to be lifted manually
Right: a mezzanine section with completely installed plates

The mezzanine floor must be completed before machines are installed underneath, because it holds air conditioning system, filters, lightings, electricities and other utitilites. Sandwich panels covering are to be installed later.

Kiri: sebuah plat akan diangkat secara manual
Kanan: bagian mezzanine dengan plat yang telah terpasang

Lantai mezzanine harus diselesaikan terlebih dahulu sebelum mesin-mesin diletakkan di bawahnya, karena mezzanine akan menampung instalasi ac, filter, lampu, kelistrikan dan instalasi lain. Nantinya akan ditutup dengan sandwich panel.

Wrapped Rommelag machine below mezzanine levelA visit from Klaus Schuster, the German machinary expert

Left: machines from Rommelag, Germany, still wrapped below the mezzanine
Right: A visit from Klaus Schuster, a machine expert from Germany

The bottle-making machine from Rommelag is our most expensive, and it has arrived in our factory, ready to be tested this month.

Kiri: mesin dari Rommelag, Jerman, masih dikemas di bawah mezzanine
Kanan: Kunjungan Klaus Schuster, ahli mesin dari Jerman

Mesin produksi botol dari Rommelag adalah mesin kami yang termahal, saat ini sudah berada di lokasi dan siap diujicoba bulan ini.

Pavingstones installation

Pavingstones installation is expected to be completed by early December.

Pemasangan paving diharapkan selesai pada awal Desember.

Completed pavingstones, with team MJB and team Mandiri

Team MJB and Team Mandiri, standing on the completely paved internal roadway.

As seen behind, the factory wall will be painted all white.

Tim MJB dan Tim Mandiri, berdiri di atas jalanan pabrik yang telah selesai dipaving.

Seperti terlihat di latar belakang, dinding pabrik nantinya akan dicat putih bersih.

 